Gündoğan - Solar Power Plant
Gündoğan Solar Power Plant was built in 2017 in Ceyhan district of Adana. The total power capacity is 17.450 KWp and 29.000 MWh of energy is produced annually.
Project Detail
Gündoğan SPP I | Gündoğan SPP II | |
---|---|---|
Total Power | 8.294,4 KWp | 9.158,4 KWp |
AC Power | 7.000 KW | 8.000 KW |
Annual Total Production | 13.500 MWh | 15.500 MWh |
Total Area | Place | Place |
Orientation | South 20 Degrees | South 20 Degrees |
Module | First Solar 120W | First Solar 120W |
Totale Module | 69.120 Pieces | 76.320 Pieces |
Driver | Sungrow SG60KTL | Abb Trio 50 |
Total Driver | 112 Pieces | 160 Pieces |
Year Of Construction | August 2017 | December 2017 |